Friday, June 18, 2010

New Roof, Framing & Masonry


Rear curtain wall will hold 8 upper windows and
one lower 17 foot sliding glass door

Interior view of curtain wall framing

Framing of rear curtain wall begins

Bulkhead for lighting and roof drains installed

Permits for walk-through scaffold allow masons to set up

Hydro wires have been wrapped for masonry work
on the face of the building

Two-story atrium opens up the former narrow passageway
and brings light into the building

View from front entryway through atrium shows
the curtain wall opening and garage

Masons re-purposed the original 100 year-old bricks
to complete the atrium opening

New roof goes on